We Can Wait a While for Dunwoody HS and Peachtree Charter MS Additions
Chamblee Charter HS Addition Scheduled Constuction in 2018
Employee Contract Recommendations for 2017-2018

This is a 1st for DCSD that I can remember - providing a list of the employees recommended for contracts for 2017-2018 school year.  Central Office and Principal Recommendations are in Phase II.
https://simbli.eboardsolutions.com/Meetings/Attachment.aspx?S=4054&AID=799812&MID=58907

I may be retired to the beach by the time these new school additions are complete - Good Times!!

The following timelines are taken from the ESPLOST-V Project List from the BOE Meeting on Monday night:
https://simbli.eboardsolutions.com/Meetings/Attachment.aspx?S=4054&AID=800126&MID=58907

  • Construction of new classroom addition at PCMS scheduled to begin June 2021; completion May 2023;
  • Construction of new classroom addition at Dunwoody HS scheduled to begin October 2020; completion Sept. 2022;
  • Construction of new classroom addition at Chamblee HS scheduled to begin November 2018; completion October 2020;
  • Construction of new elementary school for Cross Keys North scheduled to begin December 2018; completion July 2020;
  • Conversion of Cross Keys HS to Cross Keys MS scheduled to begin November 2018; completion June 2020;
  • Construction of new Cross Keys HS scheduled to begin September 2019; completion June 2022;
  • Construction of new classroom addition at Lakeside HS scheduled to begin July 2020; completion June of 2022.